Pilot Project 1

The project was conducted at Rivière-au-Renard in November 2016 on a 2.25 MVA power transformer installed on a 7’ x 7’ concrete base. This is an experimental wind turbine for the Gaspe Wind Farm Technical Centre (TechnoCentre Éolien de Gaspé). The collaboration of TechnoCentre Éolien staff was essential and greatly appreciated.

Pilot Project 2

Conducted in Saguenay, on a 28 MVA three-phase transformer installed on a 10’ x 20’ concrete base in an HV substation. Our hosts were the first to understand the potential of our concept and to support a pilot installation.Priceless data was gathered from both sites, which had vastly different characteristics. This allowed us to design a new-generation oil spill management system. ...